FG breaks ground on £746m (₦1.45trn) upgrade of Apapa and Tin Can ports, with 20,000 jobs expected
Poland’s export credit agency is backing the rebuild of Lagos’s two main ports. Ministers say cargo now sits for 10 to 18 days, against three to five at leading ports.

The Federal Government on Wednesday 25 November broke ground on a £746 million (about ₦1.45 trillion) modernisation of the Lagos Port Complex in Apapa and Tin Can Island Port, which it says will create at least 20,000 direct and indirect jobs, ThisDay, The Whistler and Ships & Ports reported.
Minister of Marine and Blue Economy Adegboyega Oyetola performed the groundbreaking at Tin Can Island Port, alongside the Minister of Finance and Coordinating Minister of the Economy, Taiwo Oyedele, and the Managing Director of the Nigerian Ports Authority (NPA), Abubakar Dantsoho.
What will be built
The work covers quay walls and berths, dredging of navigation channels, access facilities, cargo-handling equipment and operational systems, the outlets reported. The contractor is ITB-Hitech JV, whose managing director is Engr. Ramzi Chidiac.

The project is financed with the support of Poland’s export credit agency, KUKE, in its first Nigerian project. Oyedele described it as Nigeria’s largest sovereign export credit deal since 2009.
No completion date was given. Ships & Ports said the NPA would work to contractual timelines.
Why the government says it is needed
Oyetola said cargo dwell time at the ports was 10 to 18 days, against three to five days at leading ports, and put the cost of port inefficiency at up to $4 billion a year. The Whistler quoted him as saying, “The cost of inaction is far greater than the cost of modernisation.”
Apapa dates from 1913 and Tin Can was commissioned in 1977, ThisDay reported. Throughput has risen from 8.11 million tonnes in 1977 to 129.3 million tonnes, while Nigeria’s population has grown from about 67 million to about 240 million.
An inter-ministerial committee of the ministry, the NPA and the Nigerian Port Economic Regulatory Agency will prepare a Port Business Continuity and Cargo Flow Management Plan, covering phased construction, vessel scheduling, cargo evacuation and truck traffic.
The government has also approved modernisation of Onne, Rivers, Delta and Calabar ports, ThisDay and The Whistler said.
Who was there
Guests included Poland’s Deputy Foreign Minister Marcin Bosacki, Polish Ambassador Michal Cygan and British Deputy High Commissioner Jonny Baxter, the outlets reported.
Background
Earlier this week Oyedele invited Polish companies to invest in Nigeria, and Poland’s export credit agency said it could explore more deals, as TIMILEGIT reported. Nigeria’s merchandise trade has grown from about $17 billion to more than $100 billion a year since Tin Can opened, according to ThisDay and Ships & Ports.
What happens next
Phased construction and the cargo-flow plan come next. TIMILEGIT will report on timelines once the NPA publishes them.